Punch list follow up work

The following units will have additional work performed on Tuesday 7/26/16 312, 212, 208, 120, 102 We will need access from 9:00 am – 2:00 pm. This should be the final entry for your units. You do not need to remove blinds or furniture for this entry.  

Read More »

Completion of units

On Thursday between 9:30-11:30, we would like to schedule a punch list and walk-through for units: 312, 308, 306, 302, 212, 208, 206, 202, 120, 102 You do not need to remove blinds or furniture for this entry. If there is an item that needs attention, please contact Jeff Winther and it will be addressed….

Read More »

Window Sill install/Measure

Window sills will be installed 7/18-7/20 in units: 120, 212, 312, 208, 308, 206, 306, 102, 202, 302 and common areas   7/18/16 units with completed windows and not installed sills will be measured: 101, 201, 301, 107, 207, 307, 109, 209, 309, 111, 211, 311, 319, 322, 324, 325   8/8/16 – Cambria will…

Read More »

Bay window insulation

Construction Update: 6/27/16 Great news to all 3rd floor bay window ceilings: The construction crews will able to open up, access and get the architect and building inspector approval to insulate from the exterior. This was discussed at length prior to scheduling and after some concerns arose from some owners and residents they were able…

Read More »

Phase 2 update – Clarification 6/25/16

Good morning all, I had some questions and clarification needed for some residents. I apologize for the late response I was not in the office yesterday and had issues with remote link to be able to respond to these questions see below for clarification. The construction crew will only be working and installing windows in…

Read More »

Phase 2 update 6/10/16

Exterior siding continues this week into next week, there will be visible progress next week with the siding. The bay window siding went up a little slow, but it is going be faster and will continue to speed up and progress. The exterior stone sills are being installed as they go before siding gets completed….

Read More »

Phase 2 Update 5/24/16

Sills will be measured on 5/31/16 by Cambria – they need to enter all completed units: 312, 308, 306, 302, 212, 208, 206, 202, 120, 102 to measure all sills. The delivery time is 2-4 weeks after measure. They will be in units for under 10 minutes. The crews will continue with window installs in units…

Read More »

Construction Update 5/19/16

Next week 5/23-5/28 they will be installing siding and A/C sleeves on the south side of the building. They need to enter units 212, 312, 208, 308, 202, and 302 briefly to remove and reinstall the A/C unit. Going forward they will do the A/C sleeves at the same entry of the window installs.  

Read More »