Final Inspection for the Construction Phase II

Hello all owners, With the Smoke detectors now up to code, the final inspection for the contraction Phase II project was scheduled for Monday (January 23, 2017) at noon. We will need to get into all units (or until the inspector says he/she is satisfied) and it should take about 5 minutes for each unit. …

Read More »

Phase 2 Construction Update

Oct. 4 – Oct. 14 Crew will be finishing siding on the parking lot side (above garage entry). Anticipated completion of the siding phase will be Oct. 14. Oct. 17 – Plan to start installing new gutters The balance of October will be project detail finishing, clean up, caulking, etc.; with an anticipated completion date…

Read More »

Construction Update

Phase 2 Construction Completion Schedule is as follows: • By the end of the month, the new screen porch material should be installed. • Siding will be complete on October 14. • All other miscellaneous clean-up, cleaning and caulking will be done by October 31. Crew will also be working on Fridays to start falling…

Read More »

Update 8/31/16

Exterior siding continues on the 3rd Ave. side, they will be starting the 7th Street NE side soon. Substantial completion is expected at the end of September with some minor touch up and finishing early October. Final caulking, trim gutters, and finishing will follow the mass completion of siding install. The final warranty testing was…

Read More »

Phase 2 Update

Phase 2: 8/17/16 Window sills for the following units will be installed on August 22 and 23: 119, 125, 124, 122, 219, 225, 217, 224, 222, 220, 320 Final walk through and punch list will be done on Thursday August 25 for the above units. YOU DO NOT NEED TO REMOVE BLINDS OR WINDOW COVERINGS…

Read More »

Phase 2 Update

The parking lot side of the building has siding installed, but still has some caulking, flashing, gutters, and drip edge on the roof lines finishing to be done. This is going to be completed over the next couple weeks. Some Friday work will be done over the rest of August and September to do finishing…

Read More »

Sill installs 8/4 – 8/5

Window sills for the following units will be installed on August 4 and 5: 101, 107, 109, 111, 113, 117, 201, 207, 209, 211, 213, 301, 307, 309, 311, 313, 319, 325, 324, 322, 317 Final punch list and walk-through for the above units will be on 8/8 from 9 AM to 2 PM. The…

Read More »

Window installs will continue for the following units: 124, 224 on Monday and Tuesday    8/1-8/2 122, 220, 222, 320, 320 on Wednesday/Thursday    8/3-8/4 Please make sure pets are secure or made arrangements for. Remove all blinds, hardware, and move furniture for access to the windows Siding around the building will continue, next week is the…

Read More »