Phase 2 Update

The parking lot side of the building has siding installed, but still has some caulking, flashing, gutters, and drip edge on the roof lines finishing to be done. This is going to be completed over the next couple weeks.

Some Friday work will be done over the rest of August and September to do finishing caulking and final finishes on the project.

Exterior siding will continue for the remaining project. The white bay window siding is the first to be installed and then siding in gray and red will fill in behind.

Flashing, drip edge and roof soffits will be completed after siding.

The project will continue into September with 100% completion expected in mid October. There will be a larger crew working on siding to keep the project moving.

If there is a problem that needs attention, please contact Jeff Winther and it will be addressed.