Phase 2 update – Clarification 6/25/16

Good morning all,

I had some questions and clarification needed for some residents. I apologize for the late response I was not in the office yesterday and had issues with remote link to be able to respond to these questions see below for clarification.

The construction crew will only be working and installing windows in units that have bays from now through July 8th. After that we will go back to scheduling in stacks. 

I am sorry for the miscommunication, this changed multiple times over the last few weeks with vendor scheduling and insulation product approval.

If you have any other questions about next week schedule work please let me know and I will get back to you as soon as possible.

Again, I am sorry for the confusion and short notice on this change.