Oct. 4 – Oct. 14 Crew will be finishing siding on the parking lot side (above garage entry).
Anticipated completion of the siding phase will be Oct. 14.
Oct. 17 – Plan to start installing new gutters
The balance of October will be project detail finishing, clean up, caulking, etc.; with an anticipated completion date of October 31.
With the outside work being weather dependent, rain delays have necessitated work onsite on Fridays, which is expected to continue until the project is completed.