Phase 2 Construction Completion Schedule is as follows:
• By the end of the month, the new screen porch material should be installed.
• Siding will be complete on October 14.
• All other miscellaneous clean-up, cleaning and caulking will be done by October 31.
Crew will also be working on Fridays to start falling back and completing some of the misc. finishing touches (flashing, drip edge and roof soffits, gutters, etc.) as they go around the building.