Phase 2 update 6/10/16

Exterior siding continues this week into next week, there will be visible progress next week with the siding. The bay window siding went up a little slow, but it is going be faster and will continue to speed up and progress.

The exterior stone sills are being installed as they go before siding gets completed. The breeze way (porch in front) finishing work is now underway and we hope it will be opened by the end of the month.

The next scheduled window installs will be as follows:

  • Monday and Tuesday, June 20 & 21 for units 109, 209 309.
  • Wednesday and Thursday, June 22 & 23 for units 111, 211, and 311.


I have asked the crew to try and condense some storage space and keep the driveway areas as clear as possible, so cars can pass easily.

Few bay windows the crew worked on have had very little rot and water damage and some sills have been replaced. There have been some isolated issues, but not an alarming amount.

Rain delays have set the last couple of weeks back, but overall we’re still on schedule.

Please be prepared when your unit is scheduled for work. All blinds and blind hardware need to be removed. Thank you for your cooperation and being prepared for workers coming into your unit(s) – it allows for the project to move along smoothly.