Phase 2 Update 5/24/16

Sills will be measured on 5/31/16 by Cambria – they need to enter all completed units: 312, 308, 306, 302, 212, 208, 206, 202, 120, 102 to measure all sills. The delivery time is 2-4 weeks after measure. They will be in units for under 10 minutes.

The crews will continue with window installs in units 101, 201, 301, 5/31 – 6/1 Tuesday & Wednesday then 107, 207, and 307 Thursday and Friday 6/2-6/3.
They will not be onsite on Memorial Day, but will be working the following Friday as make up.

3rd floor bay window ceilings need to be cut open and insulated. Only the finished units (312, 308, 307, 306, 302, 320) will be entered. This is going to be a fairly invasive process. They will need access and have the area taped off for 7 days.

The schedule is as follows: This schedule has changed dates!

6/26Mask off bay area and demo all ceilings- this is going to be a plastic wall enclosing the bay window area.

6/28Insulate and have city inspector sign off

6/29Drywall ceiling patch and 1st coat of mud and tape

6/302nd coat of mud, texture prep spray if dry

Weekendoff

7/1 Paint ceilings