Phase 2 Update 5/24/16

Sills will be measured on 5/31/16 by Cambria – they need to enter all completed units: 312, 308, 306, 302, 212, 208, 206, 202, 120, 102 to measure all sills. The delivery time is 2-4 weeks after measure. They will be in units for under 10 minutes. The crews will continue with window installs in units…

Read More »

Construction Update 5/19/16

Next week 5/23-5/28 they will be installing siding and A/C sleeves on the south side of the building. They need to enter units 212, 312, 208, 308, 202, and 302 briefly to remove and reinstall the A/C unit. Going forward they will do the A/C sleeves at the same entry of the window installs.  

Read More »