Construction update 4.12.16

Window installation will be starting in units 120, 220, 320, 212, and 312 on Monday 4/18/16. Please see the attachment they will also be posted on unit doors Wednesday. After the first windows are installed and testing is preformed they will start with regular window installs and moving quickly around the building. This is expected to stare the week of April 25. Unit notices will be sent out no less than 5 days in advance.

Construction on bay window roofs will remain as scheduled working around the building and will also start installing new siding on the large blank wall areas and chimneys.

The new working hours will be 4/10 hours days starting at 8:00 AM- 6:00 PM Monday–Thursday and will leave Friday for rain make up days. This will help with productivity with extended hours 9 hour working days after clean up and start up and also limit lost rain days.

As always, if you have any questions please contact Jeff Winther, property manager/ASK.